Drinking water and sanitation 2024

Automation of a drinking water treatment plant

Municipal utility — interior of the country

22%
Energy savings
~120
Labor hours freed up per month
4
Brands integrated
0
Overpressure incidents

Challenge

The plant pumped raw water under manual control. The operator had to adjust valves and starters according to the elevated tank's demand. Wasted energy and equipment wear from direct-on-line starting.

Beiton solution

4 VLT AQUA Drive FC-202 units in master-follower cascade, 2 Samson 3241 control valves with 3730-3 positioners, a UWT NivoRadar level radar on the elevated tank, a Siemens S7-1200 PLC with a Comfort Panel HMI and SCADA integration. Operator training and an annual preventive maintenance contract.

Result

Fully automated operation. A 22% reduction in pumping energy consumption. Zero overpressure incidents since commissioning. Real-time data available to the management team.

We went from 100 % manual operation to SCADA with cascade control, on the schedule we were promised. For our people the key part was the training in the field, not just the equipment delivery.
— Operations Manager — Municipal water utility

Products used

  • VLT AQUA Drive FC-202
  • Samson 3241 + 3730-3 positioner
  • UWT NivoRadar NR 7200
  • Siemens S7-1200 + Comfort Panel

Services delivered

  • Applied engineering
  • Multi-brand integration
  • Commissioning
  • Training
  • PM contract